Pacifico Energy Korea’s offshore wind ambitions in South Korea moved a step closer to capital commitment on 3 September, when Pacifico Energy submitted an investment declaration worth more than $1bn covering the 990MW Manho and 1.8GW Jindo Baram projects to South Korea’s Ministry of Trade, Industry and Resources. The declaration was made at a US Investment Ceremony hosted by the ministry and the Korea Trade-Investment Promotion Agency, held at the Willard InterContinental Hotel in Washington DC.
Minister of Trade, Industry and Resources Kim Jung-Kwan attended alongside Pacifico Energy Korea representative director and global head of offshore wind Seung-Ho Choe. Pacifico Energy confirmed the investment will be fully allocated to the Manho and Jindo Baram developments, with no portion directed elsewhere in the portfolio.
An investment declaration is a stated intention, not a financial close. That distinction matters here, because Manho and Jindo Baram are still navigating South Korea’s regulatory pipeline. According to Yahoo Finance, applications for the Electricity Business Licences for both the 990MW Manho and 1.8GW Jindo Baram projects have been submitted and are currently under review. Until those licences are granted, the projects remain in development rather than construction.
That said, Manho and Jindo Baram were selected in August as the sole project developers for the government-designated 2.13GW Jindo Phase 2 Offshore Wind Integrated Cluster, which gives the projects a degree of regulatory standing that earlier-stage declarations typically lack. Government designation as sole developer is a meaningful threshold in South Korea’s offshore wind permitting process, and it differentiates this pledge from a purely speculative commitment.
This is also Pacifico Energy’s second such declaration. A 2024 investment declaration covered the 420MW Myeong Ryang offshore wind project and the development of the regional supply chain, establishing a pattern of staged public commitments aligned with the three-phase structure of the wider cluster.
Manho and Jindo Baram are the second and third phases of the 3.2GW offshore wind cluster that Pacifico Energy Korea is developing off Jindo County, with Myeong Ryang as the first phase. According to Pacifico Energy, the cluster represents the largest offshore wind project cluster in a single area being pursued by a single developer in the Asia-Pacific region. That is a claim worth tracking: the Asia-Pacific offshore wind pipeline is competitive, and “largest by single developer in a single area” is a specific enough formulation to be testable as more projects reach final investment decision.
Myeong Ryang, meanwhile, has progressed the furthest of the three phases. Yahoo Finance reports that it received its Electricity Business Licence in September 2025 and finalised its preliminary Environmental Impact Assessment report in March. Those two milestones, the licence and the completed EIA, are the regulatory foundations the later phases will need to replicate before they can follow the same path.
The supply chain dimension carries weight beyond the generating capacity itself. Choe’s remarks at the ceremony pointed to the broader economic rationale: ‘Pacifico Energy Korea’s offshore wind portfolio will supply clean energy to bolster Korea’s export competitiveness, while also building key infrastructure to support the semiconductor cluster and RE100-ready industrial complexes in Jeonnam-Gwangju.’
RE100 compliance, for the industrial buyers in that corridor, is increasingly a prerequisite for access to international supply chains rather than a discretionary ESG commitment. Offshore wind capacity situated close to semiconductor manufacturing represents a Scope 2 solution with genuine offtake logic, though the offtake agreements themselves have not been disclosed.
Choe also framed the wider track record at the ceremony: ‘As a leading energy infrastructure developer, Pacifico Energy has accelerated the energy transition at industrial scale across the U.S. and the Asia-Pacific region for more than a decade.’
The next concrete milestones to watch are the Electricity Business Licence decisions for Manho and Jindo Baram, currently under review. Those determinations will indicate whether the $1bn declaration firms into a fundable project or remains a headline awaiting its regulatory underpinning.